25 men are employed to do a work in, which they could finish in 20 days but they drop off by 5 men at the end of every 10 days. In what time will the work be completed?
2 Answers
The work finishes on the 24th day.
Explanation:
We start with 25 men. They can do a job in 20 days. This means that the 25 men finish
At the end of 10 days, the 25 men will have finished:
And now we drop off 5 men, leaving 20 left. We have
Now the job is
And they do. In fact, they can do the remaining work 3 times over. This means they'll finish on the 4th day:
The time taken will be
Explanation:
We are working with inverse proportion where, as the number of people decreases, the time taken to finish a task will increase.
Find the constant first.
The total task requires
In the first
For the next
The amount of work completed is:
There are then
The work can be completed in:
The total time taken is therefore
The work will be completed on the