25 men are employed to do a work in, which they could finish in 20 days but they drop off by 5 men at the end of every 10 days. In what time will the work be completed?

2 Answers

The work finishes on the 24th day.

Explanation:

We start with 25 men. They can do a job in 20 days. This means that the 25 men finish #1/20# of the job each day. This means that each man (using #m# to mean the work a man does each day) does:

#25m=1/20=>m=1/500# of the job each day.

At the end of 10 days, the 25 men will have finished:

#(1/500)(25)(10)=250/500=1/2# of the job.

And now we drop off 5 men, leaving 20 left. We have #1/2# of the job to do:

#(1/500)(20)(10)=200/500=2/5#

Now the job is #1/2+2/5=5/10+4/10=9/10# done, leaving #1/10# to do. We drop off 5 men, leaving 15. They should finish before the 10 days are up:

#(1/500)(15)(10)=150/500=3/10#

And they do. In fact, they can do the remaining work 3 times over. This means they'll finish on the 4th day:

#(1/500)(15)(3)=45/500<1/10#

#(1/500)(15)(4)=60/500>1/10#

Jul 16, 2018

The time taken will be #23 1/3# days, so the work will be completed by the #24th# day.

Explanation:

We are working with inverse proportion where, as the number of people decreases, the time taken to finish a task will increase.
Find the constant first.

#x xx y =k#

The total task requires #25 xx20 = 500# 'man-days'

In the first #10# days, #25xx10 = 250# 'man-days.', which means that the task is half completed.

For the next #10# days there are only #20# men.

The amount of work completed is: #20xx10 = 200 # 'man-days'.

There are then #15# men left to complete the remaining amount of work.

#500-250-200 =50# 'man-days'

The work can be completed in:

#50/15 = 3 1/3# days

The total time taken is therefore # 10+10+3 1/3# days

The work will be completed on the #24th# day.