Question #52237
1 Answer
Nov 1, 2017
See a solution process below:
Explanation:
If we divide
If we divide the 36 shawls by 12 days we can determine how many shawls 1 person can weave in 1 day:
Now we can multiply this by 15 to find how many shawls 1 person can weave in 15 days:
Now we can multiply this by
The answers in (C) 6 people can weave 270 shawls in 15 days.