Please solve this quick problem?

enter image source here

1 Answer
Mar 15, 2018

5 new workers

Explanation:

It takes a total of #15 times 12 = 180# man-days to complete the highway. Until the morning of the 5th day, the crew had devoted #4 times 15 = 60# man-days.

The new workforce completed the rest of the 120 man-days of work in 6 days. Thus there must now have been. #120/6=20# workers - so the number of new workers is #20-15=5#