JJ construction claims to have done two-thirds of the $1000000.00 job they were given. Can they claim $80000.00 for the job done so far?

1 Answer
Mar 16, 2018

Yes, They can claim upto $666666.67 that is $666666 and 67 cents.

Explanation:

For 1 work they were supposed to get $1000000.
So, for #2/3# parts of the work, they get #2/3 xx# $1000000
= $666666.67

That's it. Hope it helps :)