Question #a3df3

1 Answer
Oct 14, 2017

Work done = potential energy gained (in this case, GPE)

GPE= mgh

=20kg times 9.8m/s^2times 30 m

=5880J

Power ="Work"/"Time taken"

=(5880J)/(10s)

=588 "watts"